PH3 ยท Farm and Industry
ERC sends 24 show-cause orders to 13 generators over outages, and island diesel and bunker plants are on the list
SHOW-CAUSE ISSUED The orders themselves have been issued. Any penalties are only proposed at most, nothing has been decided, and the companies' verified replies weren't in as of 4 November. Power Philippines, not the ERC itself, is the source for the list of named plants.
The Energy Regulatory Commission said on 4 November it had issued 24 show-cause orders, dated 14 October, to 13 generation companies that went over the unplanned outage limits in ERC Resolution No. 23, series of 2026. Power Philippines lists the units, among them Republic Cement Batangas DPP DG1, SPC Island Power Panay DPP 1 Unit 2, Toledo Power Carmen DPP DG1, Meridian Power MPI BCFDPP Unit 6, and Therma Mobile's TMO M3 and M5 BCFDPP units.
Separately, SunStar and Newsline report the ERC and DOE inspected Therma Marine's Mobile 1 and Mobile 2 in Mindanao in September, with Therma Marine blaming fuel supply limits and bad weather that held up heavy fuel oil deliveries. No penalties have been set.
Why it matters: Diesel and bunker-fired plants are being held to the same reliability bar as baseload plants, so engine availability and fuel logistics are now a regulatory risk for operators and their service crews.
Filed by the Diesel Industry News Philippines desk.