PH4 ยท Marine
NorthPort's four hybrid cranes pair batteries with smaller diesels at Manila North Harbour
DIESEL-ELECTRIC HYBRID Port equipment. Battery and engine size not published. The 58.7 per cent figure is an emissions estimate, not a fuel saving.

ICTSI's domestic arm NorthPort has taken delivery of four Mitsui E&S hybrid rubber tyred gantry cranes at Manila North Harbour, due to start work this month. Each crane pairs a large battery storage system with a smaller diesel engine, instead of running a full size diesel the whole shift.
NorthPort says the four cranes should cut average annual carbon emissions per unit by up to 58.7 per cent compared with a traditional RTG crane. No fuel saving figure or engine size has been published.
The company is also working through Pier 14 and 16 upgrades it wants finished by 2027, as part of a wider plan to lift capacity at the terminal.
Why it matters: Diesel stays on the crane, just smaller, so port mechanics will be looking after battery systems alongside the engine from now on.
Filed by the Diesel Industry News Philippines desk.